SITUATION IDENTIFIED IN: Maintain Engineering Item Revisions (tiedm1101m000)
SITUATION DESCRIPTION:
(Reported for NT Backoffice build 15.8)
When using the session "maintain engineering item revisions" ( tiedm1101m000), and trying to launch a drawing, it gives
the following message:
" ttstpvtemul.
Shell functionality not supported by Windows NT"
SOLUTION DESCRIPTION:
It will now be possible to display the drawing attached to an engineering item revision by clicking the button "Drawing" or
using <Shift><Ctrl><D>.
The drawing file name will be read from the above session (tiedm1101m000) in form 3.
This file should exist in the directory as mentioned in the session "Maintain EDM Parameters" (tiedm0100m000) in the
field 'Directory Name for Drawing". Furthermore, the field "Display Drawing" indicates which application program should
be used to display the drawing.
In BW mode, this application must exist on the client. The name of the application should be the executable name and
should be in the PATH.
Note:
1.) It is required to have a /temp directory on the client since the application puts the file in this temporary directory for
reading and keeps it there.
2.) For this solution, it is required to have the DLL "ottdllbw" in the $BSE/tools/{...} directory. Please check if this
exists on your system and if not, contact the the support center.
This solution solves defect 365
VRC package component comp_type comp_code
B40 c1 ps pspmg0110m0 Script/Library Object pmg0110
B40 c1 ps pspmg0112m0 Script/Library Object pmg0112
B40 c1 ps pspmg0512m0 Script/Library Object pmg0512
B40 c1 ps pspmg0511m0 Script/Library Object pmg0511
B40 c1 ps pspmg0111m0 Script/Library Object pmg0111
B40 c1 ps psfrm0112m00 Script/Library Object frm0112
B40 c1 ps psfrm0111m00 Script/Library Object frm0111
Solution : 10256
VERSION: psB40_b, psB40_c
SESSION ERROR IDENTIFIED IN: Maintain Production Batches (pspmg0101m000)
PROBLEM TEXT:
When using End Items with Formula 0.5 pcs ( conversion factor of 1 rounded as 0.01 ) then when entering a batch entry
with qty=100 then a message comes up :
"Quantity ordered incorrect; Possible values are: previous: 100, next: 100.2". Still the min. batch size is 1 and 100 is a
multiple, so this message should not come up.
SOLUTION DESCRIPTION:
Fixed the calculation . Modifications in Software component marked with ID 10466-1.
VRC package component comp_type comp_code
B40 c1 ps pspmg0101m0 Script/Library Source pmgdll1008
Solution : 11340
VERSIONS: tiB40_b, tiB40_c
SITUATION IDENTIFIED IN: Maintain Production Batches (pspmg0101m000)
SITUATION DESCRIPTION:
If one enters in psfrm0112m000 (Co and Byproducts) a material , and make a link to an operation
(operation number UNEQUAL to the operation number from the session psfrm0111m000 (Materials), then a
problem in GUI: No message while validating routing and formula.
In session Production Batch Maintenance (pspmg0101m000) on the routing field the
GUI system collapses without any message (it just aborts the session/application).
Also, in ASCII mode, an incomplete message along with B-Shell message is generated.
SOLUTION DESCRIPTION:
One argument (previously commented one) added and the message (pspmg010139) is changed.
Modifications in software components have been marked with DF 12482-1
VRC package component comp_type comp_code
B40 c1 ps pspmg0101m0 Script/Library Source pmgdll1000
B40 c1 ps pspmg0101m0 Message pmg010139
Solution : 11390
VERSION(S): psB40_b, psB40_c
SITUATION VERIFIED IN: Maintain Estimated Co/By-Products (pspmg0112m000)
SITUATION DESCRIPTION:
When modify the cost allocation(s) for Co/By-Products so that the sum of allocations for Co/By-Products is 100 % (i.e. cost
allocation to main item is 0 %) a message is sometimes displayed saying "Sum of all positive cost allocations cannot exceed
100 percent " even though the sum of all allocations is 100 %.
(This problem only occurs if the user attempts to save changes (to pspmg012.ctll) immediatly.
It is possible for the Formula Item cost allocation to equal zero, this can cause errors in cost price
calculation and financial transactions.
SOLUTION DESCRIPTION:
The value of variable hold.ctll (old value of pspmg012.ctll) is reset in the after input section of the program.
The source has been modified so only correct messages are shown. Furthermore, because of complications in cost price
calculation, a formula item can not now have a cost allocation equal to zero.
This solution solves defect 12524.
VRC package component comp_type comp_code
B40 c1 ps pspmg0112m0 Script/Library Source pmg0112
B40 c1 ps psfrm0112m00 Script/Library Source frmdll0001
B40 c1 ps psfrm0112m00 Script/Library Source frm0112
Solution : 11589
VERSIONS: tiB40_b, tiB40_c
SITUATION IDENTIFIED IN: Maintain Production Batches (pspmg0101m000)
SITUATION DESCRIPTION:
When entering one material twice in the material list and these material lines add up to zero (including shrinkage), this will
result in a division by zero.
SOLUTION DESCRIPTION:
Prevented the program from dividing by zero.
This solution solves defect 12611.